May 25, 2020

Klemme Grain Project Takes Shape

Site preparation has been completed for the construction of the 750,000-bushel grain bin at Klemme. Excavation began this week for replacement of one tunnel and the main tower foundation. Not shown in this photo from last week is that the concrete contractor began setting … [Read More...]

Concrete Work Completed at Belmond Project

The 750,000-bushel bin at MaxYield's Belmond location reached a milestone recently as all concrete work for this project has been completed. These photos show the pouring of the concrete floor late last week. Since these photos all concrete was finished. The installation of … [Read More...]

Britt Grain Bin Project Nears Completion

The completion of the 750,000-bushel grain bin at our Britt location continues at a fast pace. To date, the bin is constructed, fans are attached to the bin and we anticipate that conveyor used to fill the bin will be in place by the first week of June. The installation of … [Read More...]

Whittemore Elevator Upgrades Underway

One project that has flown under the radar that will benefit grain clients at our Whittemore location is well underway. The upgrades to the west elevator at Whittemore began a few weeks ago. In these photos from late last week, contractors have the old distributor and spouting … [Read More...]

Construction Progress at MaxYield

Progress at our three grain construction projects continued last week. In these photos from Thursday, April 30 you can see that the Britt bin project (top photo) is moving along fast. Since this photo was taken more rings have been added. The middle photo reflects continued … [Read More...]

Concrete Crews Onsite for Belmond Bin Project

The busy construction schedule continues at our Belmond grain facility, also. The first two photos show crews pouring the footing foundation a week ago Saturday. As the remaining photos show, concrete crews were busy pouring the ring wall that the bin will sit upon on … [Read More...]

Foundation Forming for Klemme Grain Project

As this photo taken last Friday shows, further excavation and site preparation continues at our Klemme grain receiving location and is expected to continue throughout this week. A solid base is essential for the next step, which is forming the area for concrete. … [Read More...]

Britt Grain Bin Taking Shape

The new 750,000-bushel grain bin at our Britt location is taking shape. These photos taken Friday, show that construction crews have installed the first ring and the roof supports. The crews were hopeful to begin installing the roof panels along with mounting and wiring the … [Read More...]