July 4, 2020

Britt Grain Bin Project Nears Completion

The completion of the 750,000-bushel grain bin at our Britt location continues at a fast pace.

To date, the bin is constructed, fans are attached to the bin and we anticipate that conveyor used to fill the bin will be in place by the first week of June.

The installation of the grain reclaim will occur at a later time in the project.

All of the underground electrical work is also completed.

The contractors responsible for constructing the bin use 8-14 days as a rule-of-thumb for time to jack a bin. The Britt project took 15 days to complete, of which three to four they could not work due to weather.

 