May 25, 2020

Construction Progress at MaxYield

Britt

Progress at our three grain construction projects continued last week.

In these photos from Thursday, April 30 you can see that the Britt bin project (top photo) is moving along fast. Since this photo was taken more rings have been added.

The middle photo reflects continued focus on site preparation for the 750,000-bushel bin that is going up at Klemme. Soon, crews will be making preparations for pouring the concrete foundation.

Klemme

At Belmond late last week (bottom photo), the concrete foundation has been poured and crews are packing sand on the bottom of the foundation so that the concrete floor can be poured. It won’t be long and this bin will start taking shape also.

 

 

 

 

 

Belmond